Completed Projects


  SİNPAŞ BOSPHRUS CITY 2.ETAP 1.KISIM
Reference Number:1001
Employer:DOST İNŞAAT PROJE YÖN.A.Ş.
Project Name:SİNPAŞ BOSPHRUS CITY 2.ETAP 1.KISIM
Location: HALKALI/İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (O.G. INSTALLATIONS HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 2.200.000,00-TL
Completed Amount: 2.200.000,00-TL
Period: 330 DAYS
Start Date: 03.11.2008
End Date: 25.12.2011


  SİNPAŞ BOSPHRUS CITY 4.ETAP 1./2. KISIM
Reference Number:1002
Employer:DOST İNŞAAT PROJE YÖN.A.Ş.
Project Name:SİNPAŞ BOSPHRUS CITY 4.ETAP 1./2. KISIM
Location: HALKALI/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (O.G. INSTALLATIONS HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 2.650.000,00-TL
Completed Amount: 2.650.000,00-TL
Period: 489 DAYS
Start Date: 25.01.2010
End Date: 25.12.2011


  SİNPAŞ BOSPHRUS CITY 5.ETAP 1.KISIM
Reference Number:1003
Employer:DOST İNŞAAT PROJE YÖN.A.Ş.
Project Name:SİNPAŞ BOSPHRUS CITY 5.ETAP 1.KISIM
Location: HALKALI/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (O.G. INSTALLATIONS HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 1.500.000,00-TL
Completed Amount: 2.650.000,00-TL
Period: 120 DAYS
Start Date: 14.06.2010
End Date: 25.11.2011


  METRO CITY
Reference Number:1004
Employer:SASEL ELEKTROMEKANİK A.Ş.
Project Name:METRO CITY
Location: LEVENT/ İSTANBUL
Description: MALL RESIDENCE (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 532.000,00 USD
Completed Amount: 678.000,00 USD
Period: 185 DAYS
Start Date: 08.09.2002
End Date: 09.01.2004


  DUMANKAYA MODERN KONUTLARI
Reference Number:1005
Employer:DOST İNŞAAT PROJE YÖN.A.Ş.
Project Name:DUMANKAYA MODERN KONUTLARI
Location: BAHÇEŞEHİR/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 3.400.000,00-TL
Completed Amount: 3.400.000,00-TL
Period: 360 DAYS
Start Date: 07.01.2011
End Date: 31.12.2012


  AKKOZA PROJESİ 1. ETAP İNŞAATLARI
Reference Number:1006
Employer:GARANTİ KOZA & AKİŞ ADİ ORTAKLIĞI
Project Name:AKKOZA PROJESİ 1. ETAP İNŞAATLARI
Location: ESENYURT - BÜYÜÇEKMECE/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 4.750.000,00-TL
Completed Amount: 4.750.000,00-TL
Period: 794 DAYS
Start Date: 20.08.2010
End Date: 28.02.2011


  TOSKANA VADİSİ 2. FAZ ELEKTRİK ALT YAPI İŞLERİ
Reference Number:1007
Employer:EMAAR PROPERTIES GAYRIMENKUL GEL A.Ş.
Project Name:TOSKANA VADİSİ 2. FAZ ELEKTRİK ALT YAPI İŞLERİ
Location: HADIMKÖY/ İSTANBUL
Description: SUBSTRUCTURE (OG SUBSTRUCTURE - A.G SUBSTRUCTURE - TELEPHONE SUBSTRUCTURE - TV SUBSTRUCTURE - POWER DISTRIBUTION UNIT AND POWER PLANT CENTERS AND ENVIRONMENTAL LIGHTENING WORKS)
Total Amount: 3.669.851,98 TL
Completed Amount: 3.985.250,12 TL
Period: 570 DAYS
Start Date: 29.02.2008
End Date: 01.10.2009


  AKKOZA PROJESİ 2. ETAP İNŞAATLARI
Reference Number:1008
Employer:GARANTİ KOZA & AKİŞ ADİ ORTAKLIĞI
Project Name:AKKOZA PROJESİ 2. ETAP İNŞAATLARI
Location: ESENYURT - BÜYÜÇEKMECE/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 4.750.000,00-TL
Completed Amount: 4.750.000,00-TL
Period: 794 DAYS
Start Date: 20.08.2010
End Date: 31.12.2013


  SİNPAŞ BOSPHRUS CITY 154 KV DEPLASE İŞLERİ
Reference Number:1009
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:SİNPAŞ BOSPHRUS CITY 154 KV DEPLASE İŞLERİ
Location: HALKALI/ İSTANBUL
Description: MAIN OVERHEAD LINE UNDERGROUND DISPLACEMENT WORKS
Total Amount: 4.641.250,24-TL
Completed Amount: 4.581.553,20-TL
Period: 150 DAYS
Start Date: 15.06.2009
End Date: 03.03.2010


  FİLLİ BOYA BETEK FABRİKASI
Reference Number:1010
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:FİLLİ BOYA BETEK FABRİKASI
Location: GEBZE/ KOCAELİ
Description: ELECTRICAL INSTALLATION WORKS (A.G. HIGH AND LOW CURRENT SUBSTRUCTURE ELECTRICAL WORKS)
Total Amount: 1.135.191,00-TL
Completed Amount: 1.726.347,00-TL
Period: 405 DAYS
Start Date: 03.01.2008
End Date: 13.02.2009


  KOÇTAŞYAPI MARKETLERİ
Reference Number:1011
Employer:KOÇTAŞ YAPI MARKETLERİ TİC. A.Ş.
Project Name:KOÇTAŞYAPI MARKETLERİ
Location: KOÇTAŞ BODRUM - KOÇTAŞ BURSA - KOÇTAŞ ADAPAZARI - KOÇTAŞ AFYON - KOÇTAŞ GEBZE
Description: HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 2.364.617,00-TL
Completed Amount: 2.449.667,00-TL
Period:
Start Date: 2010 YEAR(S)
End Date: 2010 YEAR(S)


  IRAK AWAMEDICA İLAÇ FABRİKASI 8.000 M2
Reference Number:1012
Employer:PEL COMPANY (DOST İNŞAAT VE PROJE YÖN. A.Ş.)
Project Name:IRAK AWAMEDICA İLAÇ FABRİKASI 8.000 M2
Location: ERBIL/ NORTH IRAQ
Description: ELECTRICAL INSTALLATION WORKS (O.G. HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 1.530.000,00-TL
Completed Amount: 1.530.000,00-TL
Period: 815 DAYS
Start Date: 01.05.2007
End Date: 01.08.2009


  KOÇTAŞ YAPI MARKETLERİ
Reference Number:1013
Employer:KOÇTAŞ YAPI MARKETLERİ TİC. A.Ş.
Project Name:KOÇTAŞ YAPI MARKETLERİ
Location: KOÇTAŞ TRABZON - KOÇTAŞ KONYA - KOÇTAŞ KARŞIYAKA
Description: HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 1.674.299,00-TL
Completed Amount: 1.771.005,00-TL
Period:
Start Date: 2008 YEAR(S)
End Date: 2008 YEAR(S)


  ESPRİ ALIŞVERİŞ MERKEZİ
Reference Number:1014
Employer:ÖZGÜVEN MİMARLIK İNŞ. SAN. VE TİC. LTD. ŞTİ.
Project Name:ESPRİ ALIŞVERİŞ MERKEZİ
Location: ESENLER/ İSTANBUL
Description: INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 1.053.096,00-TL
Completed Amount: 968.675,00-TL
Period: 132 DAYS
Start Date: 11.04.2007
End Date: 20.08.2007


  TRABZON MİGROS
Reference Number:1015
Employer:SYG YAPI ELEMANLARI SAN. VE TİC. LTD. ŞTİ.
Project Name:TRABZON MİGROS
Location: TRABZON
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 241.995,00- TL
Completed Amount: 192.632,00- TL
Period: 33 DAYS
Start Date: 28.04.2008
End Date: 05.06.2008


  ELECTRO WORLD MARKET
Reference Number:1016
Employer:SYG YAPI ELEMANLARI SAN. VE TİC. LTD. ŞTİ.
Project Name:ELECTRO WORLD MARKET
Location:
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 217.729,00- TL
Completed Amount: 193.247,00- TL
Period: 105 DAYS
Start Date: 29.03.2008
End Date: 15.07.2008


  PMA PHILIP MORRIS ANKARA DEPO İDARİ BİNASI
Reference Number:1017
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:PMA PHILIP MORRIS ANKARA DEPO İDARİ BİNASI
Location: ANKARA
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 400.000,00- TL
Completed Amount: 423.287,69- TL
Period: 70 DAYS
Start Date: 12.11.2009
End Date: 23.02.2010


  KOÇTAŞ YAPI MARKETLERİ
Reference Number:1018
Employer:KOÇTAŞ YAPI MARKETLERİ TİC. A.Ş.
Project Name:KOÇTAŞ YAPI MARKETLERİ
Location: KOÇTAŞ ANTALYA-2 - KOÇTAŞ BEYLİKDÜZÜ - KOÇTAŞ KAYSERİ - KOÇTAŞ MALATYA
Description: HIGH AND LOW CURRENT SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS
Total Amount: 1.483.309,00-TL
Completed Amount: 1.544.554,00-TL
Period:
Start Date: 2009 YEAR(S)
End Date: 2009 YEAR(S)


  BİLGİ ÜNİVERSİTESİ
Reference Number:1019
Employer:MEPKAR İNŞAAT MAK. TURİZM SAN. TİC. A.Ş.
Project Name:BİLGİ ÜNİVERSİTESİ
Location: İSTANBUL
Description: UNIVERSITY CAMPUS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 452.756,00- TL
Completed Amount: 578.033,00- TL
Period: 180 DAYS
Start Date: 10.05.2007
End Date: 15.12.2007


  KELKİT PARKI
Reference Number:1020
Employer:PASKA PEYZAJ İNŞ. MÜŞ. SAN. TİC. LTD. ŞTİ.
Project Name:KELKİT PARKI
Location: KELKİT/ GÜMÜŞHANE
Description: ELECTRICAL INSTALLATION WORKS (ENVIRONMENTAL LIGHTENING AND O.G. WORKS)
Total Amount: 239.999,00- TL
Completed Amount: 239.999,00- TL
Period: 75 DAYS
Start Date: 11.09.2007
End Date: 04.12.2007


  MAJIDI MALL ALIŞVERİŞ MERKEZİ
Reference Number:1021
Employer:HEVA GRUP
Project Name:MAJIDI MALL ALIŞVERİŞ MERKEZİ
Location: ERBIL/ NORTH IRAQ
Description: MALL (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 650.000,00- USD
Completed Amount: 650.000,00- USD
Period: 540 DAYS
Start Date: 23.10.2007
End Date: 02.09.2009


  CMS SHOP
Reference Number:1022
Employer:SYG YAPI ELEMANLARI SAN. VE TİC. LTD. ŞTİ.
Project Name:CMS SHOP
Location: ZEYTİNBURNU/ İSTANBUL
Description: AUTOMOTIVE ACCESSORIES SALES CENTER ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT )
Total Amount: 66.187,00- TL
Completed Amount: 89.882,00- TL
Period: 60 DAYS
Start Date: 04.04.2005
End Date: 21.05.2005


  KOÇTAŞ YAPI MARKETLERİ
Reference Number:1023
Employer:KOÇTAŞ YAPI MARKETLERİ TİC. A.Ş.
Project Name:KOÇTAŞ YAPI MARKETLERİ
Location: KOÇTAŞ YAPI MARKETLERİ - KOÇTAŞ ANKARA GORDİON - KOÇTAŞ ERYAMAN - KOÇTAŞ KAYSERİ
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 1.681.673,00-TL
Completed Amount: 1.681.673,00-TL
Period:
Start Date:
End Date: 2011 YEAR(S)


  TRİLLİUM KONUTLARI
Reference Number:1024
Employer:TEMİNAT GRUBU PROJE MÜHENDİSLİK İNŞAAT VE TİCARET LTD. ŞTİ.
Project Name:TRİLLİUM KONUTLARI
Location: KURTKÖY-PENDİK/ İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS (O.G. INSTALLATIONS HIGH AND LOW SUBSTRUCTURE AND SUPERSTRUCTURE ELECTRICAL WORKS)
Total Amount: 260.000,00- TL
Completed Amount: 262.027,00- TL
Period: 420 DAYS
Start Date: 16.09.2008
End Date: 16.11.2009


  CMS SHOP
Reference Number:1025
Employer:SYG YAPI ELEMANLARI SAN. VE TİC. LTD. ŞTİ.
Project Name:CMS SHOP
Location: KOŞUYOLU/ İSTANBUL
Description: AUTOMOTIVE ACCESSORIES SALES (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 110.000,00- TL
Completed Amount: 116.119,00- TL
Period: 180 DAYS
Start Date: 07.06.2004
End Date: 08.12.2004


  HOME İSTANBUL YAPI MARKET
Reference Number:1026
Employer:HOME İSTANBUL COMPANY
Project Name:HOME İSTANBUL YAPI MARKET
Location: ERBIL/ NORTH IRAQ
Description: CONSTRUCTION MARKET (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 800.000,00- TL
Completed Amount: 753.456,00- TL
Period: 75 DAYS
Start Date: 17.01.2011
End Date: 28.03.2011


  KAYSERİ METRO GROSMARKET
Reference Number:1027
Employer:METRO GROSMARKET BAKIRKÖY ALIŞVERİŞ HİZ. TİC. LTD. ŞTİ.
Project Name:KAYSERİ METRO GROSMARKET
Location: KAYSERİ
Description: ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 890.000,00- TL
Completed Amount: 890.000,00- TL
Period: 60 DAYS
Start Date: 27.07.2011
End Date: 01.11.2011


  İNTELTEK İDDAA OFİSİ
Reference Number:1028
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:İNTELTEK İDDAA OFİSİ
Location: MASLAK/ İSTANBUL
Description: İDDAA GENERAL DIRECTORATE (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 28.926,00- TL
Completed Amount: 32.250,00- TL
Period: 50 DAYS
Start Date: 08.12.2005
End Date: 02.02.2006


  TÜRKİYE İŞ BANKASI
Reference Number:1029
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:TÜRKİYE İŞ BANKASI
Location: İSTANBUL
Description: BANK BRANCH ELECTRICAL INSTALLATION WORKS (HIGH AND LOW CURRENT)
Total Amount: 63.749,00- TL
Completed Amount: 61.929,00- TL
Period: 180 DAYS
Start Date: 01.01.2007
End Date: 30.06.2007


  AKBANK ŞUBELERİ
Reference Number:1030
Employer:DOST İNŞAAT VE PROJE YÖNETİM A.Ş.
Project Name:AKBANK ŞUBELERİ
Location: ANKARA/ İSTANBUL
Description: BANK (HIGH AND LOW CURRENT ELECTRICAL INSTALLATION WORKS)
Total Amount: 22.506,00- TL
Completed Amount: 23.330,00- TL
Period: 69 DAYS
Start Date: 23.03.2009
End Date: 16.06.2009


  SAMSUN METRO GROSMARKET
Reference Number:1031
Employer:METRO GROSMARKET BAKIRKÖY ALIŞVERİŞ HİZ.TİC.LTD.ŞTİ.
Project Name:SAMSUN METRO GROSMARKET
Location: SAMSUN
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 1.215.400,00-TL
Completed Amount: 1.215.400,00-TL
Period: 50 DAYS
Start Date: 05.10.2011
End Date: 25.12.2011


  KOÇTAŞ YAPI MARKETLERİ
Reference Number:1032
Employer:KOÇTAŞ YAPI MARKETLERİ TİC.A.Ş.
Project Name:KOÇTAŞ YAPI MARKETLERİ
Location: GAZİEMİR OPTİMUM İZMİR
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 599.400,00-TL
Completed Amount: 599.400,00-TL
Period: 65 DAYS
Start Date: 22.12.2011
End Date: 07.03.2012


  BATI ŞEHİR 1.ETAP
Reference Number:1033
Employer:EGE YAPI LTD.ŞTİ.EMLAK PAZ.İNŞ.PRJ.YÖN.VE TİC.A.Ş.ADİ ORTAKLIĞI
Project Name:BATI ŞEHİR 1.ETAP
Location: SULTANGAZİ / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 5.000.000,00-TL
Completed Amount: -
Period: 450 DAYS
Start Date: 19.06.2012
End Date: 31.12.2013


  HAMPTON BY HİLTON KAYAŞEHİR
Reference Number:1034
Employer:MAKRO SAN. VE TİC.LTD.ŞTİ.
Project Name:HAMPTON BY HİLTON KAYAŞEHİR
Location: KAYAŞEHİR / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 1.250.000,00-TL
Completed Amount: 1.250.000,00-TL
Period: 120 DAYS
Start Date: 22.11.2012
End Date: 01.08.2013


  METROGARDEN
Reference Number:1035
Employer:SUR YAPI END.SAN. VE TİC.A.Ş.
Project Name:METROGARDEN
Location: ÜMRANİYE / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 2.000.000,00-TL
Completed Amount: 2.000.000,00-TL
Period: 330 DAYS
Start Date: 25.06.2012
End Date: 18.03.2014


  İSTANBUL BRANDIUM AVM KOÇTAŞ ‎MAĞAZASI ELEKTRİK İŞLERİ
Reference Number:1036
Employer:KOÇTAŞ YAPI MARKETLERİ TİC.A.Ş.
Project Name:İSTANBUL BRANDIUM AVM KOÇTAŞ ‎MAĞAZASI ELEKTRİK İŞLERİ
Location: ÜMRANİYE/İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS(HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 414.000,00-TL
Completed Amount: 414.000,00-TL
Period: 65 DAYS
Start Date: 12.11.2012
End Date: 29.03.2013


  İSTANBUL VIALAND AVM KOÇTAŞ MAĞAZASI ELEKTRİK İŞLERİ
Reference Number:1037
Employer:KOÇTAŞ YAPI MARKETLERİ TİC.A.Ş.
Project Name:İSTANBUL VIALAND AVM KOÇTAŞ MAĞAZASI ELEKTRİK İŞLERİ
Location: EYÜP/İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS(HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 445.720,72-TL
Completed Amount: 445.720,72-TL
Period: 68 DAYS
Start Date: 12.12.2013
End Date: 31.05.2013


  CAPRICE GOLD İSTANBUL OTEL
Reference Number:1038
Employer:CAPRİCEGOLD GAYRİMENKUL YATIRIM ‎TURİZM İNŞ.VE TİC.LTD.ŞTİ.
Project Name:CAPRICE GOLD İSTANBUL OTEL
Location: BAYRAMPAŞA/İSTANBUL
Description: CEPHE AYDINLATMA SUBSTRUCTURESI ‎ELECTRICAL WORKS
Total Amount: 185.000,00-TL
Completed Amount: 185.000,00-TL
Period: 90 DAYS
Start Date: 01.04.2013
End Date: 31.12.2013


  ARTELL KOYTÜR BUYAKA OFİS PROJESİ
Reference Number:1039
Employer:ARTELL KOYTÜR TURİZM İNŞAAT SAN.VE ‎TİC.A.Ş.‎
Project Name:ARTELL KOYTÜR BUYAKA OFİS PROJESİ
Location: ÜMRANİYE/İSTANBUL
Description: OFİS PROJESİ ELECTRICAL INSTALLATION WORKS
Total Amount: 135.000,00-TL
Completed Amount: 135.000,00-TL
Period: 30 DAYS
Start Date: 02.04.2013
End Date: 01.08.2013


  GAZİANTEP FORUM AVM KOÇTAŞ MAĞAZASI ELEKTRİK İŞLERİ
Reference Number:1040
Employer:KOÇTAŞ YAPI MARKETLERİ TİC.A.Ş.
Project Name:GAZİANTEP FORUM AVM KOÇTAŞ MAĞAZASI ELEKTRİK İŞLERİ
Location: GAZİANTEP
Description: ELECTRICAL INSTALLATION WORKS(HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 374.572,54-TL
Completed Amount: 374.572,54-TL
Period: 45 DAYS
Start Date: 05.08.2013
End Date: 31.12.2013


  GÜRLE SUNİ DERİ FABRİKASI EK BİNA ELEKTRİK İŞLERİ
Reference Number:1041
Employer:GÜRLE SUNİ DERİ TEKSTİL SAN. VE TİC. A.Ş.
Project Name:GÜRLE SUNİ DERİ FABRİKASI EK BİNA ELEKTRİK İŞLERİ
Location: ÇORLU
Description: ELECTRICAL INSTALLATION WORKS
Total Amount: 160.000,00-TL
Completed Amount: 160.000,00-TL
Period: 60 DAYS
Start Date: 26.08.2013
End Date: 31.12.2013


  BEYAZIT OTEL PROJESİ ELEKTRİK İŞLERİ
Reference Number:1042
Employer:-
Project Name:BEYAZIT OTEL PROJESİ ELEKTRİK İŞLERİ
Location: GEDİKPAŞA-FATİH/İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS(HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 1.026.000,00-TL
Completed Amount: 1.026.000,00-TL
Period: -
Start Date: 01.04.2014
End Date: 31.12.2014


  STUDIO SANTRAL YURT BİNASI ELEKTRİK İŞLERİ
Reference Number:1043
Employer:SİLAHTARAĞA GAYRİMENKUL YATIRIM A.Ş
Project Name:STUDIO SANTRAL YURT BİNASI ELEKTRİK İŞLERİ
Location: EYÜP/İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS(HIGH AND LOW CURRENT ELECTRICAL WORKS)
Total Amount: 2.000.000,00- TL
Completed Amount: 2.000.000,00- TL
Period: 120 DAYS
Start Date: 15.05.2014
End Date: 31.12.2014


  BATI ŞEHİR 3.ETAP G1, G2 VE G3 BLOKLAR ELEKTRİK İŞLERİ
Reference Number:1044
Employer:EGE YAPI LTD.ŞTİ.EMLAK PAZ.İNŞ.PRJ.YÖN.VE TİC.A.Ş.ADİ ORTAKLIĞI
Project Name:BATI ŞEHİR 3.ETAP G1, G2 VE G3 BLOKLAR ELEKTRİK İŞLERİ
Location: SULTANGAZİ / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 6.900.281,24 TL
Completed Amount: 6.900.281,24 TL
Period: 350 DAYS
Start Date: 21.10.2014
End Date: 01.01.2018


  RSD OFİS NİSPETİYE CADDESİ OFİS PROJESİ ELEKTRİK İŞLERİ
Reference Number:1045
Employer:RSD İNŞAAT GAYRİMENKUL GELİŞTİRME YATIRIM SAN.TİC.LTD.
Project Name:RSD OFİS NİSPETİYE CADDESİ OFİS PROJESİ ELEKTRİK İŞLERİ
Location: BEŞİKTAŞ / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 280.000,00 TL
Completed Amount: -
Period: 60 DAYS
Start Date: 15.06.2015
End Date: 31.12.2016


  SOYAK KONFORİA 1.ETAP PROJESİ ELEKTRİK İŞLERİ
Reference Number:1046
Employer:SOYAK YAPI İNŞAAT SANAYİ VE TİCARET A.Ş.
Project Name:SOYAK KONFORİA 1.ETAP PROJESİ ELEKTRİK İŞLERİ
Location: ARNAVUTKÖY / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 2.900.000,00 TL
Completed Amount: 2.900.000,00 TL
Period: 540 DAYS
Start Date: 10.02.2016
End Date: 01.01.2018


  BATI ŞEHİR RADISSON BLU ELEKTRİK İŞLERİ
Reference Number:1047
Employer:EGE YAPI LTD.ŞTİ.EMLAK PAZ.İNŞ.PRJ.YÖN.VE TİC.A.Ş.ADİ ORTAKLIĞI
Project Name:BATI ŞEHİR RADISSON BLU ELEKTRİK İŞLERİ
Location: SULTANGAZİ / İSTANBUL
Description: ELECTRICAL INSTALLATION WORKS ( HIGH AND LOW CURRENT ELECTRICAL WORKS )
Total Amount: 4.650.000,00 TL
Completed Amount: -
Period: 340 DAYS
Start Date: 10.11.2015
End Date: 31.12.2016

-



Back to top